Saudi Kayan Ethylene Plant, Jubail

Forensic delay analysis to support an extension of time claim relating to late engineering design change on this £1 billion petrochem complex; followed by further forensic analysis of the subsequent acceleration programme to support further claims for financial recovery.

Lindsey Oil Refinery

Our personnel have had experience in the commercial management of trade packages to a number of onshore oil refineries.  At LOR pre and post contract services were provided to trade contractors engaged by turn key contractor Foster Wheeler, dealing with the commercial consequences of a number of facets including land contamination claims, temporary works to major plant lifts and 'potable water' distribution systems.

Coryton Refinery

Preparing underutilisation output claims relating to the hire of one of the worlds inshore floating cranes, hired for installation of prefabricated flare towers and distillation units.  Issues revolved around levels of liability for refinery refurbishment programming, detailed lift programmes and impact of external factors.